FPSO vessel for Greater Tortue Ahmeyim project sets off for Mauritania and Senegal
The floating production, storage and offloading (FPSO) vessel for the bp-operated Greater Tortue Ahmeyim (GTA) liquefied natural gas (LNG) project has started its journey towards the project site off the coasts of Mauritania and Senegal.
The FPSO set sail on 20 January 2023 from Qidong, China after successfully completing a series of sea trials following construction over the past three and half years. It will now travel 12,000 nautical miles via Singapore to its final destination – around 40km offshore on the maritime border of the neighbouring countries.
In a statement, bp said that the FPSO is a key part of the major integrated GTA development that also includes subsea development of gas fields and near-shore floating LNG (FLNG) facilities. The project’s first phase is set to produce around 2.3 million tonnes of LNG per year.
Rahman Rahmanov, bp’s vice president projects for Mauritania & Senegal said: “We are developing one of the world’s most unique and innovative gas projects and the FPSO forms one of the most important components. Achieving the successful sail away of the GTA Phase 1 FPSO is a testimony to the tremendous partnership with our contractors Cosco Shipping and Technip Energies.”
The FPSO will process natural gas - removing condensate, water, and other impurities - before exporting it by pipeline to the project’s FLNG facilities, 10km offshore. With eight processing and production modules, the FPSO will process around 500 million standard cubic feet of gas per day.
The majority of the gas will be liquefied by the FLNG facilities, enabling export to international markets, while some is allocated to help meet growing demand in the two host countries. Condensate will be periodically transferred from the FPSO to shuttle tankers for export to market.
Gordon Birrell, bp’s executive vice president of production and operations, said: “This is a fantastic milestone for this important project, which is a great example of bp’s resilient hydrocarbon strategy in action. The team has delivered this in a challenging environment, including through COVID, always keeping safe operations at the heart of what they do. With the continued support of our partners, Societé Mauritanienne des Hydrocarbures in Mauritania, Petrosen in Senegal and Kosmos Energy, we remain committed to helping both countries to develop their world-class resources in a sustainable way.”
GTA Phase 1 marks the beginning of a project that is expected to have a lasting and positive impact for generations to come.
KEEPING THE ENERGY INDUSTRY CONNECTED
Subscribe to our newsletter and get the best of Energy Connects directly to your inbox each week.
By subscribing, you agree to the processing of your personal data by dmg events as described in the Privacy Policy.
More gas & LNG news

Moldova Seeks Deal to Keep the Lights on After Russia Cut Gas Supply

Norway Gets First Ship to Carry Waste Carbon to Undersea Storage

ADNOC Gas delivers record $5 billion net income for 2024

Quebec Says It’s Open to LNG, Oil Projects After Trump Threats

Big Oil’s Wave of Buyouts Sets Up Next Leg of Energy IPO Rebound

Ecopetrol Shares Drop As Petro Proposes Shale Operation Sale

SoftBank, OpenAI Team Up to Develop AI for Japan Business

Exxon, Chevron Brave DeepSeek Risk to Chase AI Future as Oil Glow Fades

Chevron Starts Using ‘Gulf of America’ in Nod to Trump